Investor: Ministry of Finance, Republic of Serbia
Contract value: 2.174.312,08 EUR without TAX
Completion of works: august 2020
Complete works on the construction of the border crossing Kotroman between the Republic of Serbia and Bosnia and Herzegovina. Works are carried out during the work of the existing border crossing and include the demolition of existing buildings and the construction of new ones.